Historical Data
Compare historical costs
Compare approved project and package costs per square foot, then inspect the material unit prices behind your benchmarks.
Before you begin
- Approved historical pricing for the projects you want to compare.
- Valid building square footage for project and package cost-per-SF comparisons.
- Consistent scope, currency, and units for the comparison you intend to make.
Follow these steps
Create a dashboard chart
In Project Cost Distribution, select Create chart. Choose a market sector, a state, or both, then create the chart. Choosing both limits the chart to projects that match both selections.
Choose a trade or all project costs
Use the chart's Trade control to compare a specific package. Select All project costs to return to the overall project comparison.
Read the project count and chart labels to confirm the comparison includes the intended projects.
Read the distribution
The chart shows the average cost per SF and the spread around that average. Reference values include Average −1 SD, Average, and Average +1 SD.
Each historical project has equal weight. The average is not weighted by project square footage. A fitted normal curve describes the displayed observations; it is not a forecast or a guaranteed pricing range.
Inspect the projects behind the chart
Hover, focus, or tap a project tag or price line to see its project information. Use View plotted projects to inspect the source list. Toggle Show project lines when you want to change the chart display.
Open the linked source records before relying on a benchmark. With only one project, or no variation in prices, there may not be enough information to draw a meaningful distribution curve.
Compare packages and materials
Choose Package in the browse View dropdown to review average cost per SF by package. Expand a package to inspect its projects, and use the cost distribution control beside a rate for its chart.
Choose Materials to browse packages and groupings with approved unit costs. Expand the rows to inspect individual projects and material records. Use their unit cost distribution controls to examine the spread of comparable observations.
Use the benchmark during bid leveling
In a package's Bid Leveling tab, use the Historical Comparison row when available. Open its market sector/state filter control to refine the comparison, then apply your selections.
Review bidder prices alongside the historical chart. Current bidder markers are comparison points and do not change the historical average or standard deviation.
Choose the right comparison
| View | Best for | Verify first |
|---|---|---|
| Project | Overall project pricing and approved bid rounds. | Included packages, additional costs, area, bid date, and project scope. |
| Package | Trade-level costs per square foot. | Organization package mapping, scope coverage, location, and area. |
| Materials | Specific materials or equipment priced by unit. | Item specification, quantity unit, currency, and whether labor or installation is included. |
If a benchmark is empty or unexpected
Broaden the filters and check that matching projects have approved costs, correct package mappings, and valid areas or units. Open the source records to check differences in scope. Do not treat material-only pricing as an installed cost.